Organisation : Punjab State Power Corporation Ltd
Facility : Procedure for Release of Electric Connection
Home Page : https://www.pspcl.in/
Procedure here :https://www.pspcl.in/consumer-services/
Release of Electric Connection :
** Application by DS/NRS applicants to be made on composite Application & Agreement form (CS-1A) obtainable from local office.
Related : Kanpur Electricity Supply Company PSPCL New User Registration : www.statusin.in/21333.html
** For loads upto 10 KW single phase connection and for loads above 10 KW Three Phase connections are released.
** Application for industrial, Bulk & Agricultural connections up to 100KW can be made on composite Application & Agreement(A&A) form CS-1. 2 copies of form are required.
** For loads above 100 KW, 3 sets of agreements in Form CS-1 (HT/EHT) are to be submitted.
Supply is given at 400 volts for loads up to 100 KW.
For higher loads, the supply voltages are :
** Contract demand up to 2500 KVA 11 KV
(Contract demand above 2500 KVA and up to 4000 KVA can be catered at 11KV with 10% extra billing)
** exceeding the above limit and up to 20 MVA 33/66 KV
** exceeding 20 MVA and up to 35 MVA 66/132 KV
** exceeding 35 MVA shall be catered 132/220 KV
** Bulk Supply consumers upto 5MW 11 KV
** Bulk Supply consumers above 5MW 33KV & above
** Industrial & BS consumers with load above 500KW/500KVA are to register requisition in the office of SE/Op in form CS1(R) alongwith earnest money AT RS.100/KW for feasibility clearance & then regular A&A forms are accepted.
Application accepted with Advance Consumption Deposit at the following rates(per KW or part thereof) :
Domestic Supply : Rs.500
Non Residential Supply : Rs.700
Small Power : Rs.500
Medium Supply : Rs.750
Large Supply :
(i) General Category : Rs.1000
(ii) Power Intensive : Rs.1500
Bulk Supply : Rs.1500
Public Lighting : Rs.2000
Agriculture Power : Rs.200 per BHP
In case of Large Supply consumers ACD is recovered as under :
1. For Load up to 1000 KW : in 2 equal Instalments, one with application form and other through demand notice.
2. For loads above 1000 KW and up to 2000 KW : in 2 instalments first 25%(but not less than the first Instalment for 1000 KW) and balance 75% through demand notice.
3. For loads above 2000 KW : in 2 Instalments, first 20%(but not less then the first Instalment for 1000 KW) and balance 80% through demand notice.
** No interest shall be payable on ACD.
** Security for energy Meter (applicable wef 10/8/2000) :
LT Single Phase Energy Meter :
(a) Electro-mechanical TypeRs.600/-
(b) Electronic TypeRs.600/-
Industrial and Bulk Supply :
** Load Service Connection Charges
** Up to 1000 KW Rs.750/** per KW
** Above 1 MW Rs.750/** per KW or actual cost whichever is higher.
** Test report is to be submitted while complying with the demand notice.
** In case of DS/NRS consumers wiring contractor’s test report is considered as authentic and no verification is done to expedite the release of connection.
** Connections are released on the basis of seniority of test reports(first come first served).