tsfactories.cgg.gov.in : Approval of Plan to Construct/Take into Use Any Building as a Factory Telangana

Organisation : Department of Factories, Government of Telangana
Facility Name : Approval of Plan to Construct/Take into Use Any Building as a Factory
Applicable States/UTs : Telangana
Website : https://tgfactories.cgg.gov.in/home.do;jsessionid=D35BE3DDF328BDFFEB379BA2C9C5C79D

Sponsored Links:
Want to ask a question / comment on this post?
Go to bottom of this page.

TS Factories Approval

Approval of Plan and Permission to Construct/ Extend/ or Take into Use Any Building as a Factory

Related / Similar Facility :
Telangana Police PVC/PCC Certificate

eLaabh Telangana Benefit Management System

Sponsored Links:

How To Apply?

Please log in the https://ipass.telangana.gov.in/ to avail this service.
1. Create user login by clicking on Register in the homepage.
2. Login by using the created id and password.
3. Click on CFE.
4. Enter details in the Questionnaire.
5. Show Approvals and submit the Questionnaire.
6. Click on Common Application Form (CAF) and select the Approvals for which you intend to apply.
7. After, that enter the Enterprise Details, Location Details, Line of Activity, Power Details, and other selected details.
8. Upload the requisite Documents as per the Checklist.
9. Select to pay for Factories Department and make online payment.
10. The Application will be submitted online and the status can be tracked in the Entrepreneur Dashboard.
11. Query if any from the department will be visible on the entrepreneur dashboard.
12. Response to the query can be submitted online.
13. In case of application approved, the viewable / downloadable approval certificate will be available in entrepreneur dashboard under Approval Status.

In case of Rejection:
1. An appeal against rejected application can be made from the entrepreneur dashboard on complying with the reasons for rejection.
2. A request to consider the appeal has to be made in the help desk also.
3. In case of appeal made it would be forwarded to concern department for their actions.

Required Documents

1. Self certification Form. (Download the form check list for application under Act & Rules in the Home page)
2. Registration Deed ( Registered Sale ,lease/Rental deed)
3. Mutation Order.
4. Combined building plan including all floors.
5. Combined site plan.
6. Partnership deed or Articles of Association.
7. Flowchart.
8. Pan/ Aadhar card.

Additional Attachments:
** In case of plan extension / modification on factory building plans.
** Previously approved plans have to be annexed.

Fee

** Factories wherein the Maximum installed Horse Power is upto 100: Rs.1,000/-
** Factories wherein the Maximum installed Horse Power is from 101 to 500: Rs.3,000/-
** Factories wherein the Maximum installed Horse Power is from 501 to 1,500: Rs.5,000/-
** Factories wherein the Maximum installed Horse Power is from 1,501 to 10,000: Rs.10,000/-
** Factories wherein the Maximum installed Horse Power is above 10,000: Rs.15,000/-

Timelines

Approval of plans within 7 working days from date of submission of complete application.

Help Desk

Name of the Contact Person: Sri. V. Suryanarayana
Toll Free Number: 1800 599 3355
Sitting place: Block No: 304, 3rd Floor, Maitrivihar Comercial Complex, Besides Passport Office (Aditya Trade Center) Ameerpet, Hyderabad – 500038
Email-ID: helpdeskfactoriesdepartment[at]gmail[dot]com